INTRODUCTION

 

 
The enjoyment of opening a new building or starting up a new mechanical or electrical system can be annoying quickly if the system does not work the way the manufacturer, integrator or designers intended.  One way to help avoid this disappointment and subsequent costly refinements or repairs is commissioning.


Commissioning helps ensure that the system(s) will meet the needs of the owner and occupants.  It also verifies that the designed system meets the owner’s requirements and that construction conforms to the contract documents and the system(s) operate as needed.

Atlantis Energy Systems is thus, providing our customers with a
Commissioning Checklist intended to provide commissioning agents, architects, engineers and owners with what we believe is an appropriate method to record photovoltaic system performance at the time of start-up.  Moreover, we believe it is in the best interest of homeowners and facility managers alike, to pass this information onto their commissioning agent or others as appropriate to consider as a relevant documentation method.

 

Consider the following during the Design Phase of a project

 

Testing and commissioning of a PV system should be seriously addressed and planned during the design stage to ensure that appropriate provision is made.  We recommend that on larger projects or when USGBC LEED Certification requires, a commissioning agent is identified at an early stage of design development.  Sufficient time will be needed in the construction schedule for testing and commissioning to be adequately carried out and to ensure that any faults or equipment defects are identified and rectified.  Additionally, testing and/or balancing cannot be properly carried out under low sunlight levels so extra time will be needed for unexpected climatic weather changes.

 

Testing and commissioning requirements should be clearly stated in all phases of specifications as well as the contract specification.  Atlantis Energy Systems recommends that parameters to be tested: test conditions, test points, values expected and acceptable tolerances should be included in the projects specification as early as possible.  Our team of engineers and architects are available to your firm when these criteria are needed.  If a third party commissioning agent is required for full commissioning, this should be outlined in the specification as well.

 

Atlantis Energy Systems Recommended Commissioning Procedures

 

Visual checks will be the most simple and effective way to check the PV system components prior to and after installation.  We recommend that special attention is given the following (see 2A/3A of the Atlantis Energy Systems Checklist):

 

§         Cracked or broken glass

§         Signs of delamination or water infiltration

§         Broken, damaged or discolored cells

§         Loose electrical connections to the combiner or junction boxes and leads

 

After examining the components, electrical tests should then be carried out according to the National Electrical Code (NEC), 2005ed., Chapter 6, Article 690

§         Continuity of circuit, protective conductors, equi-potential bonding, quick connect

§         Earth electrode impedance

§         Insulation resistance

§         Polarity

§         Earth loop impedance

§         Functions of protective devices

 

For a sensible recording of the PV performance, the array commissioning tests should be carried out under a reasonable sunlight condition of global irradiance of higher than 400W/m˛onto the plane of the PV panels.  The tests should be checked against Atlantis Energy Systems’ overall system performance specification and detailed design parameters, taking into account any change made during installation.

 

We Recommend Detailed Commissioning Procedures ensuring the high performance Atlantis Energy can deliver

 

For all applications there is a Power Conversion Unit (PCU) for converting the power to a proper form for typical usages.  A series of functional testing is highly recommended to ensure that Atlantis Energy Systems are performing at its specified output.  These essential PCU tests are:

§         Anti-islanding tests (for grid connected inverters)

§         Disconnection capability for voltage and frequency disturbances (for grid connected inverters)

§         THD and individual harmonics measurements

§         Isolation between DC and AC side

§         Power Factor recording (for AC output only)

§         EMI measurements

§         Acoustic noise reduction recording

§         Visual check on markings

 

Highly recommend seeking USGBC LEED Certification using both Atlantis Energy Systems Photovoltaic products and our commissioning guidelines to gather an additional 2 to 4 points towards your Certified LEED Accredited Building or Energy Star Home

 

 

Contact our technical team for more information 630.947.5440

 

 

 

 

LEED NC For New Construction Version 2.2: Energy & Atmosphere

CREDIT

TITLE

DESCRIPTION

Prerequisite 1

Fundamental Commissioning of Building Systems

Verify proper installation, calibration and performance of HVAC systems

Prerequisite 2

Minimum Energy Performance

Establish minimum level of energy efficiency

Prerequisite 3

Fundamental Refrigerant Management

Zero use or phase-out of CFC-based refrigerants

EA Credit 1

(Up to 10 points)

Optimize Energy Performance

Incremental efficiency improvements above required baseline

EA Credit 2

(1 to 3 points)

On-Site Renewable Energy

Use of On-Site renewable energy to reduce fossil fuel impacts

EA Credit 3

(1 point)

Full Commissioning

Incorporate commissioning into the design phase and perform verification of systems beyond that of Prerequisite 1- Fundamental Commissioning

EA Credit 4

(1 point)

Enhanced Refrigerant Management

Elimination of refrigerants or early compliance with the Montreal Protocol

EA Credit 5

(1 point)

Measurement & Verification

Providing ongoing verification of building performance

EA Credit 6

(1 point)

Green Power

Support utility-sited renewable energy by purchasing Green Power

Shaded background above indicates additional credits possible when commissioning your Atlantis Energy Systems’ Photovoltaic Array

 

 

 

 

 

 

 

 


 

 

http://site.mawebcenters.com/atlantisenergy/images/horizontalblue.jpg